Uzbekistan sets a 30% local-content target for its $9.5 billion nuclear plant
President Shavkat Mirziyoyev reviewed a presentation on the progress of construction of an integrated nuclear power plant and the development of a modern satellite town in the Jizzakh region. The project entered the active construction phase on 4 June this year. Excavation of the foundation pit for the reactor building has been fully completed, with more than 1 million cubic metres of soil removed, and 450 workers and specialists are on site with more than 100 units of specialised equipment. The total cost of the project is $9.5 billion, and about 3,000 types of products and equipment are expected to be used during construction.
Local content is the point at issue. According to preliminary estimates, locally produced goods account for 21 per cent of the project, equivalent to $1.9 billion, and the president noted that this figure is insufficient. The task was set to increase that share to at least 30 per cent, to ensure that domestic enterprises carry out 65 per cent of construction and installation work, and to involve 7,000 local workers and specialists.
For this purpose it was proposed to establish a 200-hectare industrial zone in the Forish district, specialising in the production of construction materials. The zone is expected to accommodate at least 100 joint ventures and to localise production in 15 areas through technology transfer. The president approved the proposal and instructed that a draft resolution providing tax and customs benefits for participants in the zone be submitted by the end of the year.